A51 Road Works update

Highways’ contractor Amey has informed us of the following:

A51 Lichfield Road, Hopwas – Minor kerbing, and carriageway resurfacing work between School Lane and Fox Inn – 1st April 2019 for 7 weeks. See Plan-A51 Lichfield Road, Hopwas of works and residents letter Letter-A51 Lichfield Road, Hopwas Suggested diversion route Diversion Plan- A51 Lichfield Road, Hopwas

The carriageway reconstruction works of the scheme is expected to begin during week commencing 6th May 2019 for a period of 15 days, as outlined in the information below :

In the “residential section” (School Lane to River Crossing bridge) they will only close the route during the non-peak periods (9.30am to 3.30pm) to keep any disruption to a minimum.
They will undertake the majority of the work overnight in the “rural section” (Fox’ Island to River Crossing bridge) so not directly affecting any residential properties.

Here is the anticipated programme for the carriageway works;
Tuesday 7th May 2019 – School Lane to River Crossing bridge (5 days between 9.30am and 3.30pm).
Tuesday 14th May 2019 – River Crossing bridge to Fox Island (4 nights between 7.30pm and 6.00am).
Monday 20th May 2019 – School Lane to River Crossing bridge (4days between 9.30am and 3.30pm).
They anticipate being completed by 3.30pm on Thursday 24th May 2019.
There are no plans for any weekend closures.